Schedule and complete inspections

Inspections let you plan a visit to a property, record what you found against a checklist, and keep a PDF report. You find them under Operations then Inspections. Inspections are on the Professional plan and above.

  • The property and the unit being inspected must exist.
  • You need permission to create and edit inspections.
  1. Go to Operations then Inspections and select Schedule Inspection.
  2. Which property? Choose the Property, then the Unit being inspected.
  3. What kind of inspection? Choose the type: Move in, Move out, Routine, Safety, Seasonal or Ad hoc. The type is recorded on the inspection and its report; it does not add checklist items.
  4. Set the Scheduled date and confirm on the review step.

Filter the list by Status and Type.

An inspection booked on a unit is linked to the tenancy living there on the inspection day, and shows in that tenant’s portal under Visits. If the next tenancy is already signed but has not started, an inspection before its move-in date belongs to the current tenant and one after it belongs to the incoming tenant. An inspection of a vacant unit is linked to no tenancy and shows in no tenant’s portal.

Rescheduling follows the household. If you move an inspection on a unit to a day when another tenancy lives there, or when nobody does, it moves to that household: the tenants living there on the new day get the reschedule email and see the visit in their portal, and the household it moved away from is emailed that the inspection no longer concerns them and they do not need to give access. The property’s Activity tab records the move and the change of household.

Status Meaning
Scheduled Booked
Completed Findings recorded
Overdue Past its date and not completed
Cancelled Cancelled with a reason

LintelCRM also has an In progress status for inspections, but no action moves an inspection into it, so you will not see it in use.

  1. On the inspection, select Complete (Complete inspection). It is only available once the scheduled date has been reached.
  2. Set Conducted on. It cannot be in the future.
  3. The checklist starts empty. Click Add checklist item for each thing you checked, enter what was checked, and mark it Pass, Fail or N/A, with notes if needed. Every item you add must be marked.
  4. Enter the Summary (required) and any Recommendations.
  5. Switch on Has critical issues if anything needs urgent attention. On completion, the property’s agent (or the owner if no one is assigned) gets an in-app and email notification, marked high priority, saying critical issues were found. A notification is sent on every completion; it is high priority only when this is switched on.
  6. Confirm.

A completed inspection shows its findings and a Download report (PDF) button. A critical-issue warning is shown on the report.

  • Edit changes the inspection type and scheduled date.
  • Reschedule moves it to a New scheduled slot.
  • Cancel closes it; a Reason of at least 10 characters is required.

Completed and cancelled inspections cannot be edited.

The report stays with the inspection for later reference. If the inspection finds a problem, report it as a job: see Report and manage maintenance jobs. For certificates such as gas safety, see Compliance certificates.

Complete is greyed out. The inspection’s scheduled date has not been reached. Reschedule it if the date is wrong.

“Mark each checklist item Pass, Fail or N/A.” Every checklist item needs an outcome before you can complete.

“A summary is required to complete the inspection.” Add a summary of what you found.

“The report could not be downloaded.” Try again; if it keeps failing, contact support.